Street and Water Main Replacements

Hanson Court St. Reconstruction (Greater Mack to Defer) – Week of October 18th they will be doing the sidewalk and driveway prep. 

Harmon St. (Statler to Frazho) – Week of October 18th they will be doing miscellaneous concrete repairs.

Twelve Mile Road (Jefferson to Harper) – Week of October 18th the contractor has adjusted all road structures and currently doing restoration.   

Meier St. - (Joan to Rockwood)   Week of October 18th they will be doing miscellaneous punch list items.

Dorion St.  (Waterloo to east to cul-de-sac) Week of October 18th they will be doing temporary driveways, south side roadway removals and south side grade prep.

Grand Lake St. – (Harper to Greater Mack)  Watermain complete. Week of October 18th they will be doing miscellaneous concrete repairs and landscaping/restoration.

Share St. - (Harper to 13 Mile Road)  Week of October 18th they will be doing the pressure test for the water main and water services.  They will install the water main from Burton to Harper.

Maplegrove St. -  (12 Mile to Grossedale)  Date to be determined.

Brys Park – Parking Lot and Walking Path replacement.  On October 22nd the parking lot and dog park will begin.

Kyte Monroe Sports Complex – Parking Lot Replacement.  Project in progress.  October 19th they will be doing the concrete curb and gutter.

Macomb County Department of Roads Project - Nine Mile Road to 175' North of Little Mack Avenue - Cipparrone Contracting, contractor, will be placing message boards on Harper and at 10 and Little Mack announcing the project. Barrels will be set up on Monday, September 20th with saw cutting to begin on Tuesday, September 21st. Phase One will include the southbound curb lane at Taco Bell going south. This Phase will include the closing of Little Mack at Harper. They will also be closing the outside lane for equipment to remove the pavement and shift southbound traffic to the left turn lane during the day and pull the barrels back at the end of the work day. The message boards will announce this closure. Once they begin work in the intersection depending on which phase left turns will be eliminated as well.