Street and Water Main Replacements

Hanson Court (Greater Mack to Defer) – the contractor on site working on replacing the watermain.  This portion of the project should be completed by early July.  Once the water main is complete, notices will be sent regarding the reconstruction of the roadway.

Harmon St. (Statler to Frazho) – Contractor is beginning today, 7/21 to tie in the new main to the existing water main starting first at Frazho, followed by San Rosa then Statler.

Twelve Mile Road
 (Jefferson to Harper) –  The contractor will begin milling off the asphalt on the westbound lanes on Monday, July 26.  They anticipate this work will last 2-3 days.  Once the milling is complete, they will then begin on concrete repairs and drive approach work.  Those properties on the north side of 12 Mile affected will lose access to their property when the driveways are being replaced and will have to park on the nearest side street.

Meier St. - (Joan to Rockwood)  The paving contractor, Mark Anthony Construction, will begin mobilizing on Monday, July 26, 2021 to begin the project to replace the roadway.  Later this week their sub-contractor will begin removing trees that interfere with the project.  

Meier street will be closed from Joan to Little Mack to facilitate this construction. The contractor will remove the entire width of the road then replace a portion of the storm sewer.  Once the underground work is complete, they will then start preparing the road base then begin placing the new concrete.  If access to your property is from Meier Street this work will require you to park on the nearest side street during construction.  For trash pick-up please leave it out as usual on your normal collection date. 

Dorion St.  (Waterloo to east to cul-de-sac)  Contractor is working from Angeline Ct W toward Greater Mack transferring services leads to the temporary main in preparation to replace the existing main.  The process is slower on Dorion due to the water main being under the curb.

Grand Lake St.
 – (Harper to Greater Mack) – Contractor pulled 630 feet of new main yesterday. They will pull another 600 feet today, 7/21.  They anticipate the entire main will be in by Friday this week.

Share St. - (Harper to 13 Mile Road)  Road and watermain replacement.  Schedule forthcoming 

Maplegrove St. -  (12 Mile to Grossedale)  Schedule forthcoming.