Construction Projects

Hanson Court (Greater Mack to Defer) – the contractor on site working on replacing the watermain.  This portion of the project should be completed by early July.  Once the water main is complete, notices will be sent regarding the reconstruction of the roadway.

Harmon St. (Statler to Frazho) – The contractor Pamar construction, will begin the project beginning Monday, June 7.  It will begin by removing trees that need to be removed followed by replacement of the water main.  Once the water main is in place the contractor will begin replacing the storm sewer and pavement.

Twelve Mile Road (Jefferson to Harper) – The contractor will begin milling off the asphalt on the westbound lanes on Monday, July 26.  They anticipate this work will last 2-3 days.  Once the milling is complete, they will then begin on concrete repairs and drive approach work.  Those properties on the north side of 12 Mile affected will lose access to their property when the driveways are being replaced and will have to park on the nearest side street.

Meier St. - (Joan to Rockwood)   The paving contractor, Mark Anthony Construction, will begin mobilizing on Monday, July 26, 2021 to begin the project to replace the roadway.  Later this week their sub-contractor will begin removing trees that interfere with the project.  

Meier street will be closed from Joan to Little Mack to facilitate this construction. The contractor will remove the entire width of the road then replace a portion of the storm sewer.  Once the underground work is complete, they will then start preparing the road base then begin placing the new concrete.  If access to your property is from Meier Street this work will require you to park on the nearest side street during construction.  For trash pick-up please leave it out as usual on your normal collection date. 

Dorion St.  (Waterloo to east to cul-de-sac) Schedule forthcoming 

Share St. - (Harper to 13 Mile Road)  Road and watermain replacement.  Schedule forthcoming

Grand Lake St. – (Harper to Greater Mack) – Water main replacement.  Schedule forthcoming. 

Maplegrove St. -  (12 Mile to Grossedale)  Schedule forthcoming. 

Brys Park – Parking Lot and Walking Path replacement.  Schedule forthcoming. 

Kyte Monroe Sports Complex – Parking Lot Replacement.  Schedule forthcoming.

District 6 Sidewalk Program - starting June 15, 2021.  No more permits will be issued for work in this section.

District 7 Sidewalk Program – anticipated to begin mid-August.  Permits will be issued until August 1st.  All work must be completed prior to our contractor doing work on the street.  If not, the permit is no longer valid and our contractor will complete the work.